Client: Chaudhry Pervaiz Iqbal (Test Client) • Site: Plot 319, Block C, Phase 6, DHA Lahore • Real-Time Civil Execution & Structural Audits
Plot 319, Block C, Phase 6, DHA Lahore
Target Handover: Jun 2027
Contract Sum: Rs. 15,115,500 • Mobilization Advance: 0.0% (Rs. 0) • Defects Maintenance Period: 6 Months
Soil testing & architectural drawings
Stepped footings & bitumen DPC
Brickwork, rebar mesh, conduits, concrete pour
Columns, first floor slab, mumty & tank
Parapet, 1:4 plaster, chicken wire mesh
Porcelain tiles, PPRC pressure test, wiring
Paint, ash wood doors, sanitary fixtures
Addition of 350 sq.ft Terrace Room & Pergola
All civil materials, cement, steel, bricks, sand, crush, and MEP fittings are procured and guaranteed by the contractor under your package contract. Track stage-wise milestones, lab strength reports, and progress photos above.
Shuttering for Ground Floor Slab completed with 18mm marine plywood. Reinforcement rebar placing in progress (Grade 60 Mughal Steel).