5 Marla Spanish Luxury Villa (Phase 6 DHA) — Live 360° Site Tracker

Client: Chaudhry Pervaiz Iqbal (Test Client) • Site: Plot 319, Block C, Phase 6, DHA Lahore • Real-Time Civil Execution & Structural Audits

In progress PRJ-101

5 Marla Spanish Luxury Villa (Phase 6 DHA)

Plot 319, Block C, Phase 6, DHA Lahore

Plot: 5 Marla Covered: 2,400 Sq.Ft Storeys: Double Storey
Site Progress Meter
35%

Target Handover: Jun 2027

Account Balance Due
Rs. 11,515,500
Contract Value: Rs. 15,115,500
Total Cleared: Rs. 3,600,000 (24%)
Official Legal Agreement (Active & Signed) #AGR-2026-AA6EA ✓ Amended & E-Signed

Standard Construction Contract Agreement

Contract Sum: Rs. 15,115,500 • Mobilization Advance: 0.0% (Rs. 0) • Defects Maintenance Period: 6 Months

Construction Milestone Stages & Payment Releases

8 Total Stages
Stage 1 (5.00%) General
Paid & Verified

Design, Mobilization & Token Advance

Soil testing & architectural drawings

Milestone Due: Rs. 575,000
Client Paid: Rs. 1,800,000
Stage 2 (15.00%) General
Paid & Verified

Excavation, Foundation Footings & Plinth Level (DPC)

Stepped footings & bitumen DPC

Milestone Due: Rs. 1,725,000
Client Paid: Rs. 1,800,000
Stage 3 (20.00%) General
Under Construction

Ground Floor RCC Columns & Roof Slab Casting

Brickwork, rebar mesh, conduits, concrete pour

Milestone Due: Rs. 2,300,000
Client Paid: Rs. 0
Balance Due: Rs. 2,300,000
Stage 4 (20.00%) General
Upcoming

First Floor Structure & Rooftop Mumty Slab Casting

Columns, first floor slab, mumty & tank

Milestone Due: Rs. 2,300,000
Client Paid: Rs. 0
Balance Due: Rs. 2,300,000
Stage 5 (15.00%) General
Upcoming

Brickwork Completion & Internal/External Plaster

Parapet, 1:4 plaster, chicken wire mesh

Milestone Due: Rs. 1,725,000
Client Paid: Rs. 0
Balance Due: Rs. 1,725,000
Stage 6 (15.00%) General
Upcoming

Tile Flooring, Electrical Wiring & Plumbing Rough-Ins

Porcelain tiles, PPRC pressure test, wiring

Milestone Due: Rs. 1,725,000
Client Paid: Rs. 0
Balance Due: Rs. 1,725,000
Stage 7 (10.00%) General
Upcoming

Paint, Fixtures, Woodwork & Final Handover

Paint, ash wood doors, sanitary fixtures

Milestone Due: Rs. 1,150,000
Client Paid: Rs. 0
Balance Due: Rs. 1,150,000
Stage 8 (6.14%) Variation Scope
Upcoming

Additional Covered Area Construction (+350 Sq.Ft)

Addition of 350 sq.ft Terrace Room & Pergola

Milestone Due: Rs. 927,500
Client Paid: Rs. 0
Balance Due: Rs. 927,500

Structural QA/QC Lab Strength Reports

1 Verified Tests
First Floor Main Cantilever Beam
CONCRETE CRUSH • 20 Sep 2026 (28 Days Cured)
3,420 PSI
PASS

Client Approved Scope Changes (VO)

3 Variations
Amendment: Addition of 350 sq.ft Terrace Room & Pergola
Covered Area adjustment (+350 sq.ft). Total revised contract sum: Rs. 15,115,500
VO-20260921-255
Rs. 927,500
Approved
Swimming Pool & Italian Pergola Addition
Addition of 15x25 ft reinforced concrete pool with filtration system and pergola
VO-TEST-975
Rs. 1,344,000
Approved
Swimming Pool & Italian Pergola Addition
Addition of 15x25 ft reinforced concrete pool with filtration system and pergola
VO-TEST-830
Rs. 1,344,000
Approved
Turnkey Contract • Material & Civil Execution Inclusive

Contractor Managed Procurement & Structural Assurance

All civil materials, cement, steel, bricks, sand, crush, and MEP fittings are procured and guaranteed by the contractor under your package contract. Track stage-wise milestones, lab strength reports, and progress photos above.

Grade-60 & Premium Specs Included

Recent Daily Site Work Logs & Progress Reports

Field engineer logs
21 Sep 2026 Clear, 32°C

Shuttering for Ground Floor Slab completed with 18mm marine plywood. Reinforcement rebar placing in progress (Grade 60 Mughal Steel).

Labour on duty: 18