Skip to content

Agreement AGR-2026-AA6EA

Contract between M/S Sabir Construction and Chaudhry Pervaiz Iqbal

English (PEC Form) Print for Stamp Paper
بِسْمِ اللهِ الرَّحْمنِ الرَّحِيمِ

CONSTRUCTION WORKS AGREEMENT

Agreement Ref: AGR-2026-AA6EA | Date: 20 Sep 2026

This Construction Agreement (hereinafter referred to as the "Agreement") is entered into on this 20 Sep 2026 by and between:

THE CONTRACTOR:
Sabir Construction (Pvt) Ltd, having its principal registered office at F-5/1, Islamabad & DHA Phase 5, Lahore (hereinafter referred to as the "First Party").
THE CLIENT / EMPLOYER:
Chaudhry Pervaiz Iqbal, CNIC No. 35201-9876543-1, resident of House 42, Street 8, Phase 6, DHA Lahore, Contact: +92 300 8472199 (hereinafter referred to as the "Second Party").

1. SCOPE OF WORKS & PROPERTY SPECIFICATIONS

The First Party agrees to construct and deliver the works for project 5 Marla Spanish Luxury Villa (Phase 6 DHA) (Ref: PRJ-101) under TURNKEY specifications on the plot described below:

  • Plot Area: 5 Marla
  • Total Covered Area: 2,050 sq.ft
  • Storeys / Configuration: Double Storey
  • Site Location: Plot 319, Block C, Phase 6, DHA Lahore, Lahore

2. TOTAL CONTRACT SUM

The total agreed contract price for complete execution of the works according to approved architectural plans is Rs. 11,500,000 (Pakistani Rupees), payable stage-by-stage strictly as per the Milestone Schedule below.

3. STAGE MILESTONE PAYMENT SCHEDULE

Payments shall be released by the Second Party upon physical verification of each milestone stage (assisted by AI Site Visual Inspection):

# Milestone Stage Weightage (%) Target Days Amount (PKR)
1 Design, Mobilization & Token Advance
Soil testing & architectural drawings
5.00% 15 Days Rs. 575,000
2 Excavation, Foundation Footings & Plinth Level (DPC)
Stepped footings & bitumen DPC
15.00% 35 Days Rs. 1,725,000
3 Ground Floor RCC Columns & Roof Slab Casting
Brickwork, rebar mesh, conduits, concrete pour
20.00% 45 Days Rs. 2,300,000
4 First Floor Structure & Rooftop Mumty Slab Casting
Columns, first floor slab, mumty & tank
20.00% 45 Days Rs. 2,300,000
5 Brickwork Completion & Internal/External Plaster
Parapet, 1:4 plaster, chicken wire mesh
15.00% 40 Days Rs. 1,725,000
6 Tile Flooring, Electrical Wiring & Plumbing Rough-Ins
Porcelain tiles, PPRC pressure test, wiring
15.00% 45 Days Rs. 1,725,000
7 Paint, Fixtures, Woodwork & Final Handover
Paint, ash wood doors, sanitary fixtures
10.00% 30 Days Rs. 1,150,000

4. DELAY & LIQUIDATED DAMAGES

If the First Party fails to complete the construction works within the mutually agreed timeline, liquidated damages of Rs. 2,500 / day shall be applicable for every day of delay, except in cases of Force Majeure (war, riots, extreme floods, or government shutdown) or client-requested architectural revisions.

5. DEFECTS LIABILITY & DPC WARRANTY

The Contractor guarantees the structural stability of the RCC framing for a period of 10 Years, and provides a 12-Month Defects Liability Warranty for plumbing, electrical wiring, and seepage prevention post-handover.

6. DISPUTE RESOLUTION & ARBITRATION

Any dispute arising out of or in connection with this contract shall be settled amicably, failing which it shall be referred to arbitration under the provisions of the Pakistan Arbitration Act, 1940 and Pakistan Engineering Council (PEC) standard bylaws.

____________________________________
FIRST PARTY (Contractor)
For Sabir Construction (Pvt) Ltd
____________________________________
SECOND PARTY (Client)
Chaudhry Pervaiz Iqbal

Addendum #1: Additional 350 sq.ft terrace room approved.

✓ DIGITAL CLIENT AMENDMENT ACCEPTANCE & LEGAL E-SIGNATURE

This contract amendment was officially approved and digitally signed by Employer / Client Chaudhry Pervaiz Iqbal (Test Client) on 21 Sep 2026, 07:52 PM from verified IP 127.0.0.1.

Additional Approved Covered Area: +350 Sq.Ft | Revised Total Contract Sum: Rs. 15,115,500/-

Secure Digital Signature: Client Signature