Ref: AGR-2026-CAC54 | Date: 21 Sep 2026
| Net Turnkey Value: | Rs. 38,500,000/- | Covered Area: | 5,200 sq.ft |
| Mobilization Advance: | Rs. 5,775,000/- (15.0%) | Site Address: | Plot 108, Sector M-7, Lake City, Lahore, Lahore |
This Turnkey Agreement is made on 21 Sep 2026 between Malik Tariq Mehmood (Client) and M/S SABIR CONSTRUCTION (Contractor).
| # | Floor / Section | Workable Milestone Description | Weightage | Days | Amount (PKR) |
|---|---|---|---|---|---|
| 1 | General |
Mobilization Advance & Architectural Approval
Soil test approval, architectural & 3D elevations sign-off, municipal NOC, and mobilization advance.
|
10.00% | 15 Days | Rs. 3,850,000/- |
| 2 | Ground Floor |
Foundation, Plinth Level & DPC Damp Proofing
Trench excavation, 1:4:8 PCC, stepped brick footings, Grade-60 plinth beams, and double horizontal DPC with bitumen.
|
15.00% | 30 Days | Rs. 5,775,000/- |
| 3 | Ground Floor |
Ground Floor Structure & Roof Slab Pouring
Ground floor brick masonry, RCC columns, conduit piping, Grade-60 steel rebar, and slab concrete casting.
|
20.00% | 35 Days | Rs. 7,700,000/- |
| 4 | First Floor |
First Floor Structure, Rooftop Slab & Mumty
First floor structural masonry, roof slab pouring, mumty room, and 2" foam heat/waterproofing.
|
15.00% | 35 Days | Rs. 5,775,000/- |
| 5 | Finishing |
Plaster, False Ceiling & Electrical/Plumbing Rough-Ins
Internal/external 1:4 plaster, gypsum board false ceilings, Popular plumbing lines, and Pakistan Cables wiring.
|
15.00% | 35 Days | Rs. 5,775,000/- |
| 6 | Finishing |
Porcelain Floor/Wall Tiling & Solid Woodwork Doors
Master/Imported porcelain floor and bathroom tiling, granite counter-tops, Ashwood solid/semi-solid doors and wardrobes.
|
15.00% | 40 Days | Rs. 5,775,000/- |
| 7 | Finishing |
Paint, Sanitary Chinaware, Light Fixtures & Final Handover
Dulux/Berger luxury emulsion paint, Porta/Grohe chinaware & vanity sets, LED SMD lights, deep cleaning, and formal client handover.
|
10.00% | 25 Days | Rs. 3,850,000/- |
| TOTAL CONTRACT VALUE (100% Workable Stages): | 100.00% | — | Rs. 38,500,000/- | ||
|
CLIENT SIGNATURE: ___________________________ Malik Tariq Mehmood (CNIC: 35201-9988776-3) |
CONTRACTOR SIGNATURE: ___________________________ Engr. Sajjad Sabir s/o Muhammad Sabir for M/S SABIR CONSTRUCTION |